Current state: the target launch is 13 May, conditional on Security approval [Ana, 9 Apr 15:20]. The earlier 6 May date is superseded. Security review is due 29 April; remediation is excluded and remains dependent on findings [Chen, 10 Apr 10:00]. Training needs ten working days after final materials [Ben, 8 Apr 11:30].
Confirmed actions: Ana will send final materials to Ben by 26 April [Ana, 9 Apr 15:20]. Security will complete review by 29 April [Chen, 9 Apr 08:45], but the named individual owner is not specified.
Open questions: no remediation estimate can be given before findings; the thread does not say who decides whether any findings block launch; no one explicitly confirms that ten working days from 26 April fits 13 May. Reply checklist for Ana: acknowledge review/remediation distinction, ask who owns remediation and launch approval, ask Ben to confirm training timing, and avoid presenting 13 May as unconditional.