Реальный ввод
- Tasks, durations, and status
- A (Mina): finalize copy, 2 working days, not started. B (Leo): translate approved copy, 3 days, not started. C (Ravi): implement page shell, 4 days, 2 days remaining. D (Ravi): insert final copy, 1 day. E (QA, owner unassigned): accessibility and browser test, 2 days. F (Mina): publish, 0.5 day. Work starts Monday 31 August 2026.
- Dependencies and constraints
- B starts after A approval. D needs B and C complete. E follows D. F follows E and legal approval. Legal review was requested but no reviewer or duration is recorded. Ravi cannot work on C and D simultaneously. The translation vendor might be unavailable next week, but Leo is currently assigned internally.
- Planning rules
- Monday-Friday, no holidays. Target publication Friday 11 September 2026. No schedule buffer. Mina can assign QA; department head can escalate legal review. Use whole or half working days.